Skip to main content
Normal View

Dáil Éireann debate -
Tuesday, 15 Nov 1988

Vol. 384 No. 2

Written Answers. - Arterial Drainage.

77.

asked the Minister for Finance the expenditure provided for in the 1989 Estimates for arterial drainage; a breakdown of where this money will be spent; the amount provided for arterial drainage in the 1988 Estimates; the projected outcome of actual expenditure on arterial drainage in 1988; the amount spent in 1988 to date; and where it was spent.

The information sought by the Deputy is shown in tabular form as follows:

Subhead

1988 Estimate £000

1988 Expenditure to 31/10/88 £000

1989 Estimate £000

L1: Arterial Drainage Survey

250

183

250

L2: Arterial Drainage Construction

Boyle/Bonet

1,614

1,533

1,716

Blackwater

1,926

1,555

1,924

Sundries

760

607

660

Total

4,300

3,695

4,300

L3: Arterial Drainage Maintenance

East Region

1,320

1,161

1,420

West Region

1,340

1,153

1,350

South West Region

860

790

920

Sundries

100

20

21

Total

3,620

3,124

3,711

All options are being examined at present to ensure that the 1988 outturn will be as close as possible to the estimate.

78.

asked the Minister for Finance the number of names of the rivers/catchment areas where arterial drainage is in progress; in the case of each such river/catchment area (1) the date on which work started (2) the estimated date of completion (3) the total cost to date (4) the total estimated cost of completing the job and (5) the amount of the total expenditure that has been or will be recouped from the EC for each project.

The information sought by the Deputy is shown in tabular as follows:

Scheme

Commencement date

Completion date (est)

Expenditure to 31/10/88

EEC Aid received

Monaghan Blackwater

1985

1993

£10.085m

£2.69m

Boyle/Bonet

1982

1993

£15.816m

£5.06m

The latest published figures of final estimated cost are £18.5 million for the Blackwater and £25 million for the Boyle/Bonet schemes.

Top