The Defence Forces Infrastructure Development Plan (IDP) sets out a programme of project delivery for the years 2023 to 2027. The Programme reflects the complex environment in which the Defence Forces operate and the corresponding need for appropriate infrastructure to provide for accommodation and training of personnel, as well as maintenance and storage of equipment for land, sea and airborne operational requirements.
Under the programme, the following refurbishment works were carried out in Custume Barracks, Athlone in 2024 and to-date in 2025.
Year
|
Project
|
Status
|
Cost
|
2024
|
Resurfacing
|
Completed
|
€223,879
|
2024
|
Painting
|
Completed
|
€47,536
|
2024
|
EAS Enabling Works
|
Completed
|
€80,834
|
2025
|
Replacement Hangar EAS
|
Completed
|
€1,445,764
|
2025
|
Band Hall Heat Pump Installation
|
On-going
|
€338,580
|