asked the Minister for Local Government if he will indicate the number of schemes in West Cork under the Local Authorities (Works) Act, 1949, which (a) have been completed; (b) are in course of completion; (c) have been sanctioned for execution; and, further, if he will indicate the cost under each head.
Ceisteanna—Questions. Oral Answers. - Local Authorities (Works) Act Schemes.
The reply is in the form of a tabular statement which, with the permission of the Ceann Comhairle, will be circulated with the Official Report.
The following is the statement:—
1949/50 Programme |
1950/51 Programme |
|
Schemes Approved: |
||
Number |
154 |
|
Estimated Cost |
£29,900 |
£20,000 |
Schemes Completed: |
||
Number |
139 |
Nil |
Estimated Cost |
£24,600 |
|
Schemes in course of (2) completion at 31/3/1950: |
||
Number |
13 |
Nil |
Estimated Cost |
£4,547(3) |
Notes:—
(1) The council were informed that, as an interim arrangement, pending the notification of a final grant, works not exceeding in all £20,000 might be selected from 394 suitable schemes totalling £56,900 in estimated cost, which in turn is only a first selection of approved works.
(2) Latest date for which figures are available.