asked the Minister for Finance if he will state the several new works, alterations and additions required for the Department of Agriculture for which the sum of £83,800 is to be provided under sub-head B of the current estimate for Public Works and Buildings, and also if he will state the total sums actually expended on such works for that Department in each of the years ending 31st March, 1946, 1947 and 1948.
Ceisteanna—Questions. Oral Answers. - Public Works Expenditure.
The information requested is in the form of a tabular statement which, with the permission of the Ceann Comhairle, will be included in the Official Report.
DETAILS OF NEW WORKS, ALTERATIONS AND ADDITIONS FOR THE DEPARTMENT OF AGRICULTURE INCLUDED UNDER SUB-HEAD B OF THE ESTIMATE FOR PUBLIC WORKS AND BUILDINGS, 1950-51.
£ |
|
Fisheries Branch, 2 Kildare Place—Installation of Laboratory |
450 |
Land Rehabilitation Section—Additional Accommodation |
1,000 |
Botanic Gardens—Erection of New Fern House |
5,000 |
Athenry Agricultural School—Poultry Hatchery |
3,500 |
Athenry Agricultural School—Provision of Electric Power |
350 |
Ballyhaise Agricultural School—New Piggeries |
5,000 |
Clonakilty Agricultural School—Poultry Hatchery |
3,000 |
Grange Stud and Dairy Farm—Adaptations |
5,000 |
Johnstown Castle—Adaptations and Renovations |
36,000 |
Munster Institute—Introduction of Shannon Electric Power |
350 |
Munster Institute—Poultry Hatchery |
4,500 |
Veterinary College—Improvements |
1,650 |
Veterinary Research Institute—New Premises |
4,000 |
FISHERY, ETC., HARBOURS: |
|
Dredging Operations |
7,000 |
Works of Economic Development |
7,000 |
TOTAL |
£83,800 |
TOTAL SUMS EXPENDED ON NEW WORKS, ALTERATIONS AND ADDITIONS FOR THE DEPARTMENT OF AGRICULTURE UNDER SUB-HEAD B OF THE VOTE FOR PUBLIC WORKS AND BUILDINGS FOR THE THREE YEARS ENDED 31ST MARCH, 1948.
£ |
s. |
d. |
|||
Year ended 31st March, 1946 |
19,416 |
6 |
4 |
||
,, ,, ,, 1947 |
12,292 |
13 |
1 |
||
,, ,, ,, 1948 |
9,505 |
8 |
2 |
asked the Minister for Finance if he will state the several new works and additions for his Department for which £84,950 is to be provided under sub-head B of the current Estimate for Public Works and Buildings; and, further, if he will state the total sums actually expended on such works for his Department in each of the years ending 31st March, 1946, 1947 and 1948.
The information requested is in the form of a tabular statement which, with the permission of the Ceann Comhairle, will be included in the Official Report.
DETAILS OF NEW WORKS, ALTERATIONS AND ADDITIONS FOR THE DEPARTMENT OF FINANCE INCLUDED UNDER SUB-HEAD B OF THE ESTIMATE FOR PUBLIC WORKS AND BUILDINGS, 1950-51.
£ |
|
Dublin, Iveagh House—Office Accommodation and Staff Restaurant |
30,000 |
Dublin Castle—Renovations |
550 |
Dublin Custom House—Improvement of lay out of Grounds |
1,500 |
Dublin Custom House—West Courtyard approach—Alterations |
450 |
Dublin, Inland Revenue, 14/15 Upr. O'Connell Street—Additional Sanitary Accommodation |
500 |
Lifford Customs and Excise—Official Garage and Married Quarters |
3,000 |
Waterford Government Offices—Erection |
5,000 |
Office of Public Works—Central Engineering Workshop and Stores—New Premises |
20,000 |
Cenetaph |
12,000 |
HARBOURS: |
|
Buncrana—Improvements |
1,050 |
Dún Laoghaire—Provision of Crane |
8,600 |
Dún Laoghaire—Public Lighting |
2,300 |
TOTAL |
£84,950 |
TOTAL SUMS EXPENDED ON NEW WORKS, ALTERATIONS AND ADDITIONS FOR THE DEPARTMENT OF FINANCE UNDER SUB-HEAD B OF THE VOTE FOR PUBLIC WORKS AND BUILDINGS FOR THE THREE YEARS ENDED 31ST MARCH, 1948.
£ |
s. |
d. |
|||
Year ended 31st March, 1946 |
7,837 |
18 |
11 |
||
,, ,, ,, 1947 |
3,838 |
17 |
2 |
||
,, ,, ,, 1948 |
31,810 |
7 |
4 |