Ceisteanna—Questions. Oral Answers. - Town and Regional Planning Acts.

Mr. O'Higgins

asked the Minister for Local Government whether he has since 1st January, 1952, received any application or applications under the Town and Regional Planning Acts, 1934 to 1939, for an Order declaring compensation payable in respect of an interim direction by a planning authority; and, if so, if he will state in relation to such or each such application (a) the date on which the application was received and (b) the date the Order was made.

As the reply is in the form of a tabular statement I propose, with your permission, a Cheann Comhairle, to circulate it with the Official Report.

Following is the statement:—

TOWN AND REGIONAL PLANNING ACTS.

APPLICATIONS FOR ORDERS DECLARING COMPENSATION TO BE PAYABLE IN RESPECT OF INTERIM DIRECTIONS BY PLANNING AUTHORITIES.

No.

Date of application

Decision on Appeal

Date of Decision on Application

Remarks

1

29/1/52

Dismissed15/5/52

Submission in support of application not yet received.

2

5/2/52

Allowed16/4/52

No decision required.

3

16/2/52

Dismissed18/6/52

18/6/52

4

25/3/52

Allowed23/12/52

No decision required.

5

4/4/52

Allowed19/5/52

No decision required.

6

22/4/52

Deferred

Tentative agreement reached. Awaiting result of Compulsory Purchase Order.

7

1/5/52

Dismissed2/12/52

2/12/52

8

9/5/52

Withdrawn

Withdrawn.

9

13/6/52

Dismissed24/10/52

Submission in support of application not yet received.

10

19/6/52

Submission in support of appeal and application not yet received.

11

7/10/52

12

28/10/52

Allowed11/2/53

No decision required.

13

31/10/52

Awaiting decision on appeal.

14

20/11/52

do.

15

17/12/52

do.

16

1/1/53

do.

17

12/1/53

do.

NOTE: In each case, except No. 11, an appeal was made concurrently with the application for an Order declaring compensation to be payable.

Mr. O'Higgins

asked the Minister for Local Government if he will state whether he has since the 1st January, 1952, received any appeal or appeals under the Town and Regional Planning Acts, 1934 to 1939; and, if so, will he state in relation to such appeal or each of such appeals (a) the date on which the appeal was received and (b) the date of the decision.

As the reply is in the form of a tabular statement, I propose, with your permission, a Cheann Comhairle, to circulate it with the Official Report.

Following is the statement:—

TOWN AND REGIONAL PLANNING ACTS. z

Valid appeals received excluding those which were withdrawn formally or may be regarded as withdrawn.

No.

Date of Receipt

Date of Decision

1

1/1/52

31/3/52

2

3/1/52

22/2/52

3

4/1/52

31/3/52

4

4/1/52

Architect expected to revise proposal.

5

5/1/52

14/3/52

6

8/1/52

7/10/52

7

14/1/52

9/4/52

8

14/1/52

29/2/52

9

16/1/52

9/5/52

10

17/1/52

23/7/52

11

17/1/52

9/4/52

12

17/1/52

3/10/52

13

17/1/52

22/5/52

14

19/1/52

14/3/52

15

23/1/52

5/3/52

16

28/1/52

15/5/52

17

29/1/52

16/4/52

18

29/1/52

15/5/52

19

4/2/52

22/5/52

20

4/2/52

18/6/52

21

5/2/52

16/4/52

22

6/2/52

14/3/52

23

8/2/52

25/7/52

24

8/2/52

18/6/52

25

9/2/52

18/6/52

26

12/2/52

11/7/52

27

16/2/52

18/6/52

28

18/2/52

15/5/52

29

19/2/52

16/4/52

30

20/2/52

24/10/52

31

21/2/52

15/5/52

32

25/2/52

28/4/52

33

25/2/52

Awaiting reply from Appellant.

34

26/2/52

28/4/52

35

1/3/52

15/5/52

36

4/3/52

15/5/52

37

5/3/52

2/9/52

38

5/3/52

25/7/52

39

7/3/52

15/5/52

40

14/3/52

28/4/52

41

14/3/52

15/5/52

42

18/3/52

28/4/52

43

20/3/52

18/6/52

44

25/3/52

23/12/52

45

25/3/52

15/5/52

46

26/3/52

10/7/52

47

26/3/52

15/5/52

48

27/3/52

Appellant deceased.

49

28/3/52

2/7/52

50

29/3/52

24/10/52

51

1/4/52

28/4/52

52

3/4/52

2/7/52

53

4/4/52

19/5/52

54

7/4/52

2/12/52

55

11/4/52

21/8/52

56

12/4/52

2/7/52

57

15/4/52

19/5/52

58

18/4/52

18/6/52

59

22/4/52

Tentative agreement. Awaiting result of C.P.O.

60

23/4/52

18/6/52

61

28/4/52

2/7/52

62

28/4/52

11/7/52

63

30/4/52

24/10/52

64

30/4/52

1/10/52

65

30/4/52

Deferred pending representations by Appellant.

66

1/5/52

2/12/52

67

1/5/52

Awaiting result of special survey.

68

1/5/52

11/7/52

69

7/5/52

24/10/52

70

8/5/52

18/6/52

71

9/5/52

18/6/52

72

9/5/52

7/11/52

73

9/5/52

74

13/5/52

75

14/5/52

18/6/52

76

15/5/52

1/8/52

77

15/5/52

1/10/52

78

16/5/52

Deferred pending negotiations.

79

19/5/52

21/8/52

80

20/5/52

81

22/5/52

2/12/52

82

23/5/52

1/10/52

83

23/5/52

2/7/52

84

27/5/52

21/8/52

85

29/5/52

29/10/52

86

29/5/52

2/9/52

87

30/5/52

24/10/52

88

31/5/52

89

3/6/52

90

6/6/52

18/11/52

91

7/6/52

21/8/52

92

11/6/52

2/7/52

93

11/6/52

1/10/52

94

12/6/52

95

13/6/52

24/10/52

96

17/6/52

17/9/52

97

18/6/52

98

19/6/52

Representations by Appellants awaited.

99

19/6/52

100

26/6/52

3/10/52

101

28/6/52

21/8/52

102

1/7/52

1/8/52

103

7/7/52

24/10/52

104

8/7/52

18/11/52

105

10/7/52

Deferred pending negotiations. See also No. 78 re adjoining property

106

12/7/52

25/11/52

107

14/7/52

6/1/53

108

14/7/52

Deferred pending negotiations. See also No. 105 re adjoining property.

109

14/7/52

1/10/52

110

15/7/52

1/10/52

111

18/7/52

1/10/52

112

21/7/52

24/10/52

113

23/7/52

Proposal being revised.

114

23/7/52

24/10/52

115

23/7/52

17/9/52

116

24/7/52

24/10/52

117

30/7/52

Awaiting information from Appellant.

118

5/8/52

119

5/8/52

120

5/8/52

2/12/52

121

7/8/52

122

7/8/52

18/11/52

123

8/8/52

18/11/52

124

13/8/52

Appellant reconsidering proposal.

125

22/8/52

24/10/52

126

26/8/52

6/1/53

127

27/8/52

128

27/8/52

129

28/8/52

18/11/52

130

29/8/52

18/11/52

131

3/9/52

24/10/52

132

4/9/52

133

4/9/52

18/12/52

134

5/9/52

18/12/52

135

9/9/52

Awaiting decision as to application of bylaws.

136

12/9/52

23/12/52

137

12/9/52

138

15/9/52

139

17/9/52

18/12/52

140

17/9/52

2/12/52

141

24/9/52

Deferred pending negotiations.

142

26/9/52

18/11/52

143

1/10/52

144

3/10/52

145

6/10/52

25/11/52

146

7/10/52

147

9/10/52

2/12/52

148

11/10/52

2/1/53

149

16/10/52

150

15/10/52

Awaiting information from Appellant.

151

16/10/52

152

17/10/52

153

22/10/52

154

28/10/52

22/1/53

155

28/10/52

156

28/10/52

157

29/10/52

28/1/53

158

31/10/52

159

31/10/52

160

31/10/52

161

31/10/52

Appellant considering revision o proposals.

162

8/11/52

163

8/11/52

164

11/11/52

165

12/11/52

166

14/11/52

6/1/53

167

15/11/52

168

14/11/52

169

18/11/52

170

18/11/52

171

20/11/52

Deferred at Appellant's request.

172

20/11/52

173

15/11/52

174

24/11/52

175

24/11/52

176

25/11/52

177

26/11/52

178

28/11/52

179

28/11/52

180

2/12/52

181

2/12/52

182

3/12/52

183

4/12/52

184

4/12/52

185

5/12/52

186

5/12/52

187

9/12/52

188

9/12/52

189

9/12/52

190

12/12/52

191

12/12/52

Grounds of Appeal not yet received.

192

12/12/52

193

12/12/52

194

15/12/52

195

16/12/52

196

17/12/52

197

17/12/52

Grounds of Appeal not yet received.

198

22/12/52

199

1/1/53

200

1/1/53

201

2/1/53

202

2/1/53

203

5/1/53

Grounds of Appeal not yet submitted.

204

9/1/53

205

12/1/53

206

13/1/53

207

13/1/53

Grounds of Appeal not yet submitted.

208

14/1/53

209

16/1/53

210

20/1/53

211

26/1/53

212

26/1/53

213

24/1/53

214

28/1/53

215

29/1/53

216

31/1/53

217

2/2/53

218

2/2/53

219

4/2/53

220

3/2/53

Top
Share