asked the Minister for Local Government the date on which the present scheme in Ballymun is expected to be complete; and what other Dublin Corporation building schemes are due for completion this year, giving the units of accommodation involved.

I understand that the 3,021 dwellings in the original Ballymun project will be completed before the 31st March, 1969, and the additional 239 dwellings by 31st July, 1969.

The information requested regarding other schemes to be completed this year is not available in my Department at this stage.