Written Answers. - National Primary Road Network.

226.

asked the Minister for the Environment if he will indicate for 1988 the number of major improvements-new roads which will be carried out to the national primary road system; and if he will provide for each county and county borough the following information: (a) the national primary roads to be improved i.e. N7, N11 etc. (b) the location of the improvement-new road (c) the length of the improvement-new road (d) the cost of the improvement-new road (e) the commencement date for the improvement-new road (f) the employment directly involved in the works and (g) whether the work will be done by direct labour or by private contractor; and if he will make a statement on the matter.

Provision has been made in the 1988 road grant allocations for expenditure this year on 22 major road schemes which, when completed, will form part of the network of national primary routes. Details of these schemes, in respect of which grant allocations totalling £51 million have been notified for this year, are set out in the following table.

Details of direct employment on individual schemes are not available in my Department. It is estimated, however, that the direct employment content of this expenditure will be about 1,200 man-year-jobs, apart from the spin-off employment. A further £16 million has been allocated this year in respect of other major road projects.

Policy regarding the carrying out of future major schemes by contract or direct labour will be set out in the blueprint for road development which I intend to publish within the next few months.

TABLE

Local Authority

Route Number

Name of Scheme

Location

Length in Kilometres

Estimate of Cost £m

Date of commencement

Method of undertaking works

(a) County Council

Clare

N18

Bunratty By-Pass

Bunratty

5.0

10.5

1986

contract and direct labour

Cork

N8

Glanmire By-Pass

Glanmire

7.5

28.0

1986

contract and direct labour

N20

Cork/Mallow Road

Cork/Mallow

17.0

32.0

1986

direct labour

Donegal

N13

Port Road/ Manorcunningham

Letterkenny

9.1

10.5

1985

direct labour

Dublin

N4

Lucan By-Pass

Lucan

4.1

16.0

1985

contract

*

Dublin Ring Road

Tallaght Rd. /Lucan Rd.

8.9

36.0

1987

contract

*

Dublin Ring Road

Lucan Rd./ Navan Rd.

3.3

Private Sector Funding

1988

contract

Kerry

N22

Killarney By-pass

Killarney

3.5

3.5

1985

contract and direct labour

Mayo

N5

Turlough/Castlebar

Castlebar

7.5

3.5

1988

contract and direct labour

Meath

N3

Navan Inner Relief

Navan

3.7

7.0

1983

direct labour

Sligo

N4

Sligo Bridge

Sligo

1.5

4.0

1987

contract

N4/17

Collooney By-Pass

Collooney

3.2

3.5

1987

direct labour

Tipperary (SR)

N8

Cahir By-Pass

Cahir

6.0

7.0

1985

contract and direct labour

Westmeath

N6

Athlone By-Pass

Athlone

9.0

35.5

1983

contract and direct labour

Wexford

N11

Wexford By-Pass

Wexford

8.0

10.0

1980

contract and direct labour

Wicklow

N11

Newtownmount- kennedy

Newtownmount- kennedy

5.2

13.0

1985

contract and direct labour

(b) County Boroughs

Cork

*

Northern Ring Road

Cork City

1.9

6.5

1984

contract and direct labour

*

Southern Ring Road

Cork City

7.4

22.0

1985

contract and direct labour

Dublin

N4

Chapelizod

Chapelizod

3.0

16.0

1985

contract

N4

Johns Bridge

Kilmainham

1.2

6.0

1988

contract

Limerick

*

Mallow St. Bridge(and approaches in Limerick County)

Mallow St.

3.8

10.0

1984

contract and direct labour

Waterford

N25

Dock Road

Dock Road

0.3

3.5

1985

contract

*Route number not yet determined.