Under the local authority swimming pool programme, which is administered by my Department, there are four stages in a swimming pool project, following the submission of a feasibility study. These, in order of progress, are preliminary report, contract documents, tender and construction. My Departments technical advisers, the Office of Public Works, Office of Public Works, evaluate each stage, and local authorities cannot proceed to the next stage of a project unless prior approval issues from my Department.
The maximum grant available under the programme is €3.8 million, subject to the total grant not exceeding 80% of the eligible cost of the project or, in the case of projects located in designated disadvantaged areas, 90% of the eligible cost. Grant aid is allocated only when tenders have been approved for the project and the grant amount is capped at the time of allocation. Support is available towards the cost of the swimming pool, toddler pool, sauna and steam room.