195 Mr. Kehoe asked the Minister for Community, Rural and Gaeltacht Affairs the number of reports awaiting publication in his Department; the name of each such report; the length of time which has elapsed since each report was commissioned; the cost or projected cost of each report; and the date on which each report will be published; and if he will make a statement on the matter. [18561/05]

View answer

Written answers

The details of reports where there is an intention of publication in my Department are set out in the following appendix. For the sake of completeness, I can inform the Deputy that, in addition, my Department's annual report 2004, and statement of strategy 2005-07 are in preparation internally and are expected to be completed and published by the end of June 2005.

Name

Date Commissioned

Cost or Projected Cost

Projected Date of Publication

Staidéar Teangeolaíoch ar Úsáid na Gaeilge sa Ghaeltacht

Aibreán 2004

€550,223

Deireadh Fómhair 2006

Report of the Steering Group on the Mid-Term review of the National Drugs Strategy

Mid-2004

€74,431 (paid to consultants). Total cost of publication not yet known

June 2005

Expenditure Review of the Local Drugs Task Forces

June 2004

€79,618 (paid to consultants). Total cost of publication not yet known.

Not yet known

Athbhreithniú Caiteachais ar na Scéimeanna Feabhsúcháin sa Ghaeltacht

Meitheamh 2004

€35,000 (measta)

Mí Iúil 2005

Tuarascáil Tionscnaimh an Aire Gnóthaí, Pobail, Tuaithe & Gaeltachta (faoi Alt 5 d’Acht na dTeangacha Oifigiúla 2003) maidir le hoibriú an Achta sin.

Is tuarascáil inmhéanach a bheidh le leagan faoi bhráid Tithe an Oireachtais amháin atá i gceist agus dá bhrí sin ní bheidh ach costas ainmniúl i gceist.

Meán Fomhair 2005