154 Mr. Ó Fearghaíl asked the Minister for Defence the nature and extent of improvement works undertaken at the Defence Forces training centre at the Curragh since 2002; the amount spent on such works since; when the Defence Force headquarters will be locating to the Curragh; and if he will make a statement on the matter. [8633/07]

View answer

Written answers

My Department is engaged in an on-going capital and maintenance programme designed to modernise and enhance the training, operational and accommodation facilities available to the Defence Forces both Permanent and Reserve.

The programme focuses mainly on infrastructural projects such as the construction of new buildings, the refurbishment of existing buildings and major civil engineering works. This is complemented by an annual programme of on-going maintenance.

Since 2002 the total amount spent in the Curragh is in excess of €24 million. The following table which I propose to circulate in the Official Report details the major projects undertaken in the Curragh from 2002-2006.

A Government decision on decentralisation, announced by the Minister for Finance in his Budget statement on 3 December 2003 provides for the transfer of 300 Defence Forces headquarters staff to the Curragh, Co. Kildare. It is anticipated that Defence Forces Headquarters will relocate to the Curragh by late 2009.

Defence Forces Training Centre

Building and Engineering Projects 2002-2006

Status

Project

Date Placed

Cost

Completed

Refurb. Officers Mess Kitchen, Pearse Bks.

04-Sep-02

628,762.38

Completed

Container Storage Yard

09-Sep-02

996,939.92

Completed

I T Ducting

12-Sep-02

202,239.96

Completed

Upgrade of Sewage System

18-Oct-02

663,619.14

Completed

Computer Simulation Building — Pearse Bks.

13-Nov-02

207,303.98

Completed

Security Fencing to Storage Bld. Compound

01-Jul-03

72,640.00

Completed

Special Storage Buildings

18-Sep-03

2,114,034.22

Completed

Field Wiring etc, Phase 1

31-Oct-03

40,646.64

Completed

Reinstalment of Spraybake Unit

14-Oct-04

143,329.22

Completed

Combinrd Vehicle Workshop

02-Jan-02

9,038,649.45

Completed

Southern Boundary Security Fencing

26-Jul-02

166,175.94

Completed

Upgrade of Sewage System

18-Oct-02

711,345.58

Completed

Field Wiring etc, Phase 2

31-Oct-03

202,017.63

Completed

Renov. Equipment Storage Building

31-Oct-03

225,614.73

Completed

Plunkett Bks — Spray Paint Workshop

05-Feb-04

267,233.34

Completed

Const. Workshop and Office Facility, Plunkett

31-Aug-04

1,749,941.65

Completed

Conversion of Drawing Office Etc.

09-Sep-04

165,056.51

Completed

Reinstalment of Spraybake Unit

14-Oct-04

143,329.22

Completed

Construction of HQ Block

18-Oct-04

370,536.76

Completed

Security Fencing — Various

14-Dec-04

146,900.19

Completed

Refurbishment of McDermott Bks

11-Mar-05

832,134.94

Completed

Refurb. Block 7, Connolly Bks

18-Aug-05

1,585,195.31

Completed

CIS Stores Heating — 5 Block, Connolly

18-Aug-05

193,644.00

Completed

Heating etc, 1st Floor Plunkett

19-Aug-05

150,715.00

Completed

Sports Changing Facility

29-Sep-05

788,158.32

Completed

A D R — Storage Facility

29-Jun-06

459,713.62

In Progress

Infantry School Refurbishment

07-Jul-06

1,352,413.03

In Progress

Installation of Sheep Grids

10-Oct-06

321,058.58

In Progress

Security Works to Armoury (West)

10-Oct-06

333,805.00

In Progress

Replacement of Windows

12-Dec-06

123,081.67

TOTAL

24,396,235.93