Dáil Éireann Debate, Thursday - 10 July 2008

Thursday, 10 July 2008

Questions (47)

Brendan Howlin

Question:

41 Deputy Brendan Howlin asked the Minister for Communications, Energy and Natural Resources the amount and percentage of wind power with access to the national grid; the number of applications awaiting access to the grid; and if he will make a statement on the matter. [28023/08]

View answer

Written answers

The latest data published by EirGrid to December 2007 show that a total of c. 800 megawatts (MW) of wind-powered generating capacity is connected; there is a further 1600 MWs which have connection offers under Gate 1 and Gate 2 and a further 4000 MW approximately awaiting connection offers under Gate 3. I understand that a further 4000 MW have applied to GATE 3 since the start of 2008. The Gate 3 projects are being assessed by the Commission for Energy Regulation which is currently conducting a consultation process.