1396 Deputy Pat Breen asked the Minister for the Environment, Heritage and Local Government the situation regarding the status of the Feakle, Quilty, Mullagh sewerage treatment plants in County Clare; the delay in progressing the design build and operate for the plants; when he expects this process to be finalised; and if he will make a statement on the matter. [29874/08]

View answer

Written answers

Funding of €8.808m has been approved under my Department's Water Services Investment Programme 2007-2009 in respect of the Feakle, Scarriff and Quilty (including Mullagh) Sewerage Scheme. Under devolved procedures the wastewater collection works are a matter for Clare County Council. The Council's tender recommendation for the provision of the wastewater treatment plants is under examination in my Department.