Swimming Pool Projects.

Dáil Éireann Debate, Tuesday - 21 October 2008

Tuesday, 21 October 2008

Questions (297)

Caoimhghín Ó Caoláin

Question:

386 Deputy Caoimhghín Ó Caoláin asked the Minister for Arts, Sport and Tourism the status regarding the swimming pool in Stranorlar, County Donegal; and if he will make a statement on the matter. [35582/08]

View answer

Written answers

Under the Local Authority Swimming Pool Programme there are four principal stages in a swimming pool project which are: Feasibility Study/Preliminary Report; Contract Documents; Tender and Construction. Grant-aid is allocated only when tenders have been approved for the project and is capped at the time of allocation. My Department approved the Preliminary Report for the Ballybofey / Stranorlar Swimming Pool Project in May 2007, allowing Donegal County Council to move on to the next stage which is the preparation of Contract Documents. I understand from Donegal County Council that the Contract Documents will be submitted to my Department for approval in October 2008.

Top
Share