Schools Building Projects.

Dáil Éireann Debate, Tuesday - 24 February 2009

Tuesday, 24 February 2009

Questions (406)

Caoimhghín Ó Caoláin

Question:

444 Deputy Caoimhghín Ó Caoláin asked the Minister for Education and Science the number of schools that have been approved to go to tender and construction for the years 2006, 2007 and 2008 and have yet to proceed to construction. [6955/09]

View answer

Written answers

Currently in my Department's school building and modernisation programme, there are 74 projects at stage 3 (55 at primary and 19 at post primary level) which have been approved to proceed to tender and construction but are not yet on site. These projects include the 10 which I announced in January of this year and the 43 which I announced earlier this month. There are currently 28 projects in construction (20 at primary and 8 at post primary level).