Schools Building Projects.

Dáil Éireann Debate, Wednesday - 22 April 2009

Wednesday, 22 April 2009

Questions (680)

Emmet Stagg

Question:

732 Deputy Emmet Stagg asked the Minister for Education and Science if a preferred tender has been chosen for the contract to build the new National School at Kill, County Kildare; if the contract has been signed; and the details of the time frame for completion of the contract. [15830/09]

View answer

Written answers

A letter of intent issued to the main contractor on 9 April 2009, requesting sight of certain important documents and confirmation of a number of other issues. Once all the documentation requested has been received and meets my Department's requirements, a formal letter of acceptance will issue to the Contractor. It is estimated that it will take 12 to 15 months to complete the project, from the date of commencement on site.