The new post primary school project for Gorey, Co. Wexford is one of eight schools which I approved for inclusion in the 3rd Bundle of schools to be procured via Public Private Partnership.
This bundle is in the pre procurement stage. Detailed output specifications and Public Sector Benchmark (PSB) are being finalised and outline planning permission has been received in the case of seven of the eight schools. Work is continuing on securing outline planning permission on the remaining school site. On successful completion of this process, it is my intention that the Bundle will be handed over to the National Development Finance Agency (NDFA) for procurement.
The indicative timeframe for the delivery of a PPP school currently stands at approximately 4 years from the date the Bundle is announced.