Schools Building Projects.

Dáil Éireann Debate, Tuesday - 9 February 2010

Tuesday, 9 February 2010

Questions (572, 573)

Bobby Aylward

Question:

703 Deputy Bobby Aylward asked the Minister for Education and Science if he will appoint a design team to progress the application for an extension and refurbishment works to a school (details supplied) in County Kilkenny in view of the fact that the population in the catchment area has increased by 70% on the previous census and the increase of pupils attending this school has warranted the appointment of an additional teacher from September 2010; and if he will make a statement on the matter. [6682/10]

View answer

Written answers

I can confirm that the school to which the Deputy refers has made an application to my Department for large scale capital funding. The application has been assessed in accordance with the published criteria for large scale capital projects and has been assigned a Band 2 rating. Information in respect of the current school building programme along with assessed applications for major capital works, including the project referred to by the Deputy, are now available on my Department's website at www.education.ie.

The progression of all large scale building projects, including the project in question, from initial design through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However in light of current competing demands on the capital budget of my Department, it is not possible to give an indicative timeframe for the progression of the project at this time. In the meantime, it is open to the school authority to apply for temporary accommodation, if the need arises, pending the delivery of its large scale building project.

Sean Fleming

Question:

704 Deputy Seán Fleming asked the Minister for Education and Science if he is satisfied that all payments in respect of a contract signed by his Department in respect of a project (details supplied) in County Laois have been fully utilised directly on the project; if there is a mechanism in place to ensure that all persons who are suppliers for the project will be paid in respect of material and services provided for the project which is the subject of a contract signed by his Department; and if he will make a statement on the matter. [6688/10]

View answer

My Department entered into a contract with the main contractor to deliver a new school building for the school referred to by the Deputy. All certificates for payment which have been presented to my Department have been paid to the main contractor in accordance with the contract. No contractual relationship exists between my Department and any of the sub-contractors on this project. In this regard it is a matter for sub-contractors to agree terms and conditions for payment with the main contractor or other sub-contractors on this project.

Question No. 705 answered with Question No. 678.