I can confirm that in May 2008, my Department offered the school to which the Deputy refers, an all-in devolved grant for the provision of an 80m2 mainstream classroom. I understand the project was completed in July 2009.
In June 2010, the school was approved funding to build a further 80m2 mainstream classroom and three 16m2 learning support rooms.
The school subsequently requested that the funding be increased to permit the construction of additional accommodation to include two mainstream classrooms, principal's office, parents' room, staffroom, toilets and cleaner's store. The school was advised in a letter in July 2010 that the Department was not in a position to grant the additional funding sought in this case. However, the school were advised to complete and submit a formal application for Grant Aid for Major Capital Works for the additional accommodation sought and to proceed with the works approved in June. To date the school has neither submitted the application nor drawn down the significant funding approved in June 2010.