77 Deputy Bernard J. Durkan asked the Tánaiste and Minister for Education and Skills the extent of any over or under expenditure, capital or current, by Vote, heading or subheading to date in 2010 in tabular form; the reason for any surplus or shortfall; if expenditure to date in each case is in line with budgetary projections; and if she will make a statement on the matter. [44655/10]

View answer

Written answers

Based on the expenditure information for the period to end October 2010, it is estimated that current expenditure for my Department for the year will be in accordance with the Voted Allocation. It is possible as the end of the year approaches that excesses of expenditure on a small number of subheads will require to be offset by savings on other subheads. There is currently in this regard a projected excess of €43 million on expenditure on Student Supports (Subhead E1), due in large part to a signficant increase in numbers of grant-holders and of numbers in receipt of higher rates of grant. This projected excess will be offset by lower expenditure on Residential Institutions Redress (Subhead B12 — €10 million), anticipated savings linked to the timescale for payments being made by the Commission on Child Abuse (Subhead B19 — €12 million) and by various savings on staff costs and on FAS Programmes (€21 million).

In relation to Capital expenditure, there are indications of a potential under-spend of €62 million on the Primary subhead F1. Prominent factors in the potential under-spend include the continuing reduction in the value of tenders (40% lower than in the height of the construction boom) and financial difficulties within the sector which have delayed project delivery. It is proposed to reallocate this projected under-spend by increasing by €20 million the allocation for Schools Information and Communication TechnologIes (Subhead B18) and by transferring €42 million to the higher education capital programme (Subhead F3).

In order to facilitate the above current and capital transfers I will be seeking a technical Supplementary Estimate for my Department.

EDUCATION AND SKILLS

I. Supplementary Estimate of the amount required in the year ending 31 December 2010 for the salaries and expenses of the Office of the Minister for Education and Skills, for certain services administered by that Office and for the payment of certain grants and grants-in-aid.

One thousand euro

€1,000

II. Subheads under which this Vote will be accounted for by the Office of the Minister for Education and Skills.

2010

Original Estimate

Revised Estimate

Current

Capital

Current

Capital

Additional Sum Required

€’000

€’000

€’000

€’000

€’000

B.18

— Schools Information And Communication Technologies Activities

13,578

43,000

13,578

63,000

20,000

E01

— Student Support

324,449

367,449

43,000

F03

— An túdaras um Ard-Oideachas — Building Grants And Capital Costs For Universities and Colleges, Institutes of Technology, Disignated Institutions of Higher Education and Research and Development (Grant-in-Aid)

126,890

168,890

42,000

TOTAL:

338,027

169,890

381,027

231,890

105,000

Less:

Savings on Subheads

B.12

10,000

B.19

12,000

F.01

62,000

G.02

20,999

The total Original Net Estimate, 2010 was

8,668,104

Sum now required

1

Total

8,668,105