279. Deputy Seán Kenny asked the Minister for the Environment; Community and Local Government when the remaining phase of maisonette remedial works (details supplied) in Dublin 17 will commence; and the timescale for the completion of the project. [40106/12]

View answer

Written answers

My Department issued budget approval of some €3.6 million to Dublin City Council for this project in 2012.

It is a now matter for Dublin City Council to progress the project to construction stage. I understand the City Council expect work to commence later this year and anticipate a completion date of mid-2013.