For the Design Build Operate Finance (DBOF) PPP contracts the following projects are subject to partial Indexation at CPI/HICP:
Criminal Courts of Justice
Convention Centre Dublin
Schools - Pilots
Schools 1
Schools 2
Schools 3
Cork School of Music
National Maritime College
M50
All operating payments under the toll roads (First Roads PPP Programme) – are subject to CPI.
The Department of Environment Community and Local Government have provided the below list of Water Services DBO contracts which are in Operation and Maintenance phase as of now. It should be noted that the Department of Environment, Community and Local Government do not hold details on all projects, these details are held by the relevant Local Authority. The annual payment for operations made to the contractors by local authorities are subject to indexation from the date of tender. On contracts procured since 2008, this is based on CPI but on contracts procured prior to then indexation is based on other indices published by CSO.
Contracts subject to indexation based on CPI
WSA
|
Location
|
Status
|
Contract Signed
|
O&M Phase Commenced
|
O&M Phase Ends
|
Clare
|
Feakle/Scariff/Quilty WWTPs
|
O&M Phase
|
2009
|
2011
|
2031
|
Cork County
|
Kinsale WWTP
|
O&M Phase
|
2008
|
2010
|
2030
|
Donegal
|
Donegal Group A
|
O&M Phase
|
2008
|
2008
|
2028
|
|
Letterkenny WWTP
|
O&M Phase
|
2011
|
2012
|
2032
|
Dun Laoghaire / Rathdown
|
Shanganagh WWTP
|
O&M Phase
|
2009
|
2012
|
2032
|
Fingal
|
Portrane/Donabate/Rush/Lusk WWTP
|
O&M Phase
|
2010
|
2012
|
2032
|
Kerry
|
Kilcummin/Barraduff WWTPs
|
O&M Phase
|
2009
|
2011
|
2031
|
|
Firies WWTP
|
O&M Phase
|
2009
|
2011
|
2031
|
|
Milltown WWTP
|
O&M Phase
|
2009
|
2011
|
2031
|
Kildare
|
Kildare Town WWTP
|
O&M Phase
|
2010
|
2012
|
2032
|
Kilkenny
|
Kilmacow WWTP
|
O&M Phase
|
2010
|
2010
|
2030
|
Laois
|
Portlaoise WWTP
|
O&M Phase
|
2009
|
2011
|
2031
|
Leitrim
|
Carrick-on-Shannon WWTP
|
O&M Phase
|
2009
|
2011
|
2031
|
|
Leitrim Villages bundle DBO
|
O&M Phase
|
2009
|
2011
|
2031
|
Limerick City
|
Clareville WTP
|
O&M Phase
|
2008
|
2010
|
2030
|
Mayo
|
Kiltimagh WWTP
|
O&M Phase
|
2008
|
2010
|
2030
|
|
Castlebar WWTP
|
O&M Phase
|
2010
|
2012
|
2032
|
North Tipperary
|
Templemore WWTP
|
O&M Phase
|
2008
|
2010
|
2020
|
Offaly
|
Tullamore WWTP
|
O&M Phase
|
2010
|
2012
|
|
Sligo
|
Sligo WWTP
|
O&M Phase
|
2008
|
2010
|
2030
|
Westmeath
|
Mullingar WWTP
|
O&M Phase
|
2009
|
2011
|
2031
|
Wexford
|
Bunclody WWTP
|
O&M Phase
|
2008
|
2010
|
2030
|
|
New Ross WWTP
|
O&M Phase
|
2008
|
2010
|
2030
|
Wicklow
|
Wicklow Town WWTP
|
O&M Phase
|
2008
|
2010
|
2030
|
* Note that the capital cost has been paid upfront to the DBO contractor in stages over the Design-Build Phase so the contractor has not financed any of the capital works.