196. Deputy Pat Deering asked the Minister for Education and Skills the total amount of money allocated and the total amount drawn down for prefab replacements, new build, and upgrade, refurbishment and extension to Carlow schools, both primary and post-primary, on a school-by-school basis for 2011, 2012 and to date in 2013. [44564/13]

View answer

Written answers

I propose in the answer to indicate the level of funding provided by my Department to all schools in County Carlow for the years 2011, 2012 and to date in 2013 under the categories Large Scale projects, Additional Accommodation projects and Prefab Replacement Initiative projects.PRIMARY2011 Large Scale Projects - €3.979m

2011 Additional Accommodation Projects - €0.812m

2011 Prefab Replacement Initiative Projects - €0m

2012 Large Scale Projects - €5.690m

2012 Additional Accommodation Projects - €1.323m

2012 Prefab Replacement Initiative Projects - €0.115m

2013 (to date) Large Scale Projects - €4.565m 2013 (to date) Additional Accommodation Projects - €0.815m

2013 (to date) Prefab Replacement Initiative Projects - €0.252m

POST-PRIMARY2011 Large Scale Projects - €0.026m

2011 Additional Accommodation Projects - €0.070m

2011 Prefab Replacement Initiative Projects - €0m

2012 Large Scale Projects - €0.004m

2012 Additional Accommodation Projects - €0.014m

2012 Prefab Replacement Initiative Projects - €0.739m

2013 (to date) Large Scale Projects - €0.298m 2013 (to date) Additional Accommodation Projects - €0.036m

2013 (to date) Prefab Replacement Initiative Projects - €0.317m