I propose to take Questions Nos. 139 to 142, inclusive, together.
My Department is committed to working closely with Tuath Housing Association and Dublin City Council in resolving the structural and related issues affecting the 60 Tuath-owned properties at Gallery Quay. An updated report from Tuath on the progress to date in resolving water ingress and dampness at the Gallery Quay apartments was received by my Department on 20 June. The report is currently under examination and my Department will be in contact again with Tuath once this has been completed.
The report indicates that Tuath propose to undertake a detailed internal and external inspection of the windows and that the results of this inspection will build on the survey work carried out to date and inform the preparation of a schedule of works and tender documents, details of which are expected to be submitted to my Department in July. In advance of receiving this documentation, it is not possible to indicate the extent of necessary refurbishment works or the estimated cost of such works.