Questions (81)

Michael Moynihan

Question:

81. Deputy Michael Moynihan asked the Minister for Public Expenditure and Reform the number of reports from external consultants commissioned by his Department in the years 2012, 2013 and to date in 2014; the costs incurred by his Department to commission these reports; and if he will make a statement on the matter. [42590/14]

View answer

Written answers

In response to the Deputy's question the following table outlines the total amount spent on external reports commissioned by my Department since its inception in 2011:

Name of External Report

Costs

Date of Commission

Date or Expected Date of Publication

Name of External Consultant

Independent verification of savings arising under the Public Service Agreement

€35,819.80

16 May 2011

June 2011

MKO Partners Ltd

Report on Reasons Behind Voter Behaviour in the Oireachtas Inquiry

Referendum 2011

€41,043.20

23 November 2011

January 2012

Red C Research and Marketing Ltd.

Options for the next National Lottery licence

€615 (including VAT)

7th February 2012

2 March 2012

Davy Corporate Finance

Independent verification of savings arising under the Public Service Agreement

€31,586.40

23 March 2012

13 June 2012

Grant Thornton

Capacity and Capability Review of Central Procurement Function

€30,750.00

May 2012

6 September 2012

Accenture

ICT-MF Executive Assessment

€30,750.00

August 2012

November 2012

Innovation Value Institute, NUIM

Independent verification of savings arising under the Public Service Agreement

€24,206.40

4 February 2013

3 July 2013

Grant Thornton

Debt Management Final Report

€110,000 plus VAT

Q2 - 2013

Published 24th July 2014

BearingPoint

Report of a Consultation with Civil Society Representatives and Citizens on Ireland's Participation in the Open Government Partnership

 

 

Funding of €25,735.25 was provided to Transparency International Ireland in 2013 following a competitive tender process to support a public consultation with civil society and the preparation of a report of their recommendations and proposals for potential inclusion in Ireland's Open Government Partnership National Action Plan.

10 June 2013

Published on 2 October 2013

Transparency International, Ireland

Capacity & Capability Review of the Estate Portfolio function of the Office of Public Works (excluding Heritage Services)

€130,000.00 + VAT

12 November 2013

Report has been received by the Office of Public Works and circulated to staff

 

Concerto Partners LLP

Open Data project:

- Best Practice Handbook

- Data Audit Report

- Roadmap for Open Data

- Evaluation Framework

- Open Data Publication

Handbook

€19,188.00

3 March 2014

July 2014

Insight Centre for Data Analytics, NUI Galway

Development of Training & Organisation Development

€22,900

March 2014

July 2014

(date is approximate, relates to draft Report)

Baker Tilly Ryan Glennon.

Trinity House, Charleston Road, Ranelagh, Dublin 6

Value for Money Report of Dublin Castle's Conference Facilities

€4,674.00 Incl Vat.

7 April 2014

Qtr 3, 2014

Newmarket Consulting

Fund Structuring Services Agreement for Social Housing and Energy Efficiency in Ireland

€26,766.65

27 February 2014

5 November 2014

European Investment Bank

In the course of its normal business activity, the Office of Public Works engages technical consultants on many of its projects, primarily architectural and engineering. The costs of these consultants would be included in the overall project costs and are not included here.