Skip to main content
Normal View

Electricity Transmission Network

Dáil Éireann Debate, Thursday - 20 November 2014

Thursday, 20 November 2014

Questions (158, 159)

Martin Heydon

Question:

158. Deputy Martin Heydon asked the Minister for Communications, Energy and Natural Resources if he will provide an update on the work to date of the expert panel reviewing the Grid Link project; if it has appointed any external advisers; when he expects its work to be completed; and if he will make a statement on the matter. [44677/14]

View answer

Martin Heydon

Question:

159. Deputy Martin Heydon asked the Minister for Communications, Energy and Natural Resources his views on an extension of the terms of reference of the independent expert panel reviewing the Grid Link and Grid West projects to incorporate a review of the overall need for Grid25; and if he will make a statement on the matter. [44681/14]

View answer

Written answers

I propose to take Questions Nos. 158 and 159 together.

In January 2014, an independent panel of experts, chaired by Mrs Justice Catherine McGuinness, was established to examine the Grid West and Grid Link projects. The Panel met on several occasions since then to consider and approve the terms of reference for comprehensive, route specific studies and reports of fully undergrounded and overhead options for each of the Grid West and Grid Link projects. The studies and reports are required to include assessments of potential environmental impacts, technical efficacy and cost factors. The terms of reference for the works to be carried out were published in May and are available on my Department’s website.

EirGrid will either undertake or commission the necessary work in accordance with those terms of reference set by the Panel. In due course, the Panel will provide an opinion to me on the completeness, objectivity and comparability of the studies and reports and will oversee the publication by EirGrid of the two studies and reports prior to EirGrid proceeding to public consultation on the two projects. The Panel expects to be in a position to provide an opinion to me on the Grid West project in Q1 2015. An opinion on the Grid Link project is expected in Q3 2015.

In relation to the Grid25 Strategy, the overall strategy was forecast to cost up to €4 billion at its launch in 2007. EirGrid reviews all projects and strategies at regular intervals to take into account relevant developments including economic conditions and electricity demand forecasts. In 2010, a review of Grid25 resulted in EirGrid reducing the estimated cost of the programme to €3.2 billion. EirGrid is currently undertaking a further review which it expects to complete in Q1 2015.

Top
Share