Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Wednesday - 3 December 2014

Wednesday, 3 December 2014

Questions (112)

Terence Flanagan

Question:

112. Deputy Terence Flanagan asked the Minister for Education and Skills the position regarding school funding in respect of a school (details supplied); and if she will make a statement on the matter. [46459/14]

View answer

Written answers

The project to provide permanent accommodation for the school to which the Deputy refers is currently completing Stage 2a (Developed Design) of the architectural planning process. When that stage is complete, and subject to no other issues arising, the project will progress to Stage 2b (Detailed Design) which includes applications for Planning Permission, Fire Safety Certification, Disability Access Certification and the preparation of tender documents.

The project is on the published School Building Programme to move to tender and construction in 2014/15.

Top
Share