Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 24 March 2015

Tuesday, 24 March 2015

Questions (829)

Sean Fleming

Question:

829. Deputy Sean Fleming asked the Minister for Education and Skills the position regarding a school building project (details supplied) in County Kildare; if this will be included in the next five-year plan/capital building programme; and if she will make a statement on the matter. [12108/15]

View answer

Written answers

I am pleased to advise that a major capital project for the school referred to by the Deputy is included in my Department's current 5 Year Construction Plan.

The project is at an early stage of Architectural Planning. Following a recent Pre Stage 1 meeting, which was held in February 2015, the Board of Management and their Design Team have been authorised to progress to Stage 2(a), which is the developed sketch design stage. Upon successful completion of stage 2(a) and subject to no issues arising, this project will be authorised to proceed to Stage 2(b) - Detailed Design Stage, which includes applications for Planning Permission, Fire Safety Certification, Disability Access Certification and the preparation of tender documents.

The project will be progressed on to the tender and construction stages as soon as the architectural planning process is completed.

Top
Share