340. Deputy Ruth Coppinger asked the Minister for Education and Skills if she will provide funding for the completion of building works for a school (details supplied) in Dublin 15. [37036/15]

View answer

Written answers

The Major Building Project referred to by the Deputy is currently at an advanced Stage of Architectural Planning, Stage 2(b) which includes applications for Planning Permission, Fire Safety Certificate, Disability Access Certificate and the preparation of tender documents. All statutory approvals have been secured and the Design team have recently completed tender documents. The Department is awaiting correspondence from the Board of Management and their Design Team in order to approve Stage 2b.

School building projects, including the project in question, which have not been included in the current Five Year programme, will continue to be progressed to the final planning stages and are available to be considered in the context of the new 6 Year Construction Plan that I intend to announce in the coming weeks.

Top
Share