992. Deputy Jerry Buttimer asked the Minister for Education and Skills the details of funding provided to schools in County Cork for capital works since March 2011; including the purpose of the funding; when construction was completed, or when it is forecast to be completed; and if she will make a statement on the matter. [38160/15]

View answer

Written answers

The capital funding issued to schools in the primary and post-primary sectors in County Cork in the years 2011 to 2015 is as follows:

PRIMARY

2011 - €24.8m

2012 - €23.8m

2013 - €31.1m

2014 - €37.4m

2015 - €13.0m

POST-PRIMARY

2011 - €6.4m

2012 - €7.0m

2013 - €14.2m

2014 - €16.2m

2015 - €26.3m

It is not possible to provide the data/information requested in respect of all schools within a county. However, if the Deputy wishes to nominate a specific school, I would be happy to provide the level of capital funding issued in such an instance and when construction was completed or when it is forecast to be completed.