Flood Relief Schemes Status

Dáil Éireann Debate, Tuesday - 15 December 2015

Tuesday, 15 December 2015

Questions (181, 182, 183, 184, 185, 186)

Seán Fleming

Question:

181. Deputy Sean Fleming asked the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Cork at planning, construction and post-construction phase; the commencement and completion dates for each scheme; the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [45201/15]

View answer

Seán Fleming

Question:

182. Deputy Sean Fleming asked the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Kerry at planning, construction and post-construction phase; the commencement and completion dates for each scheme; the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [45202/15]

View answer

Seán Fleming

Question:

183. Deputy Sean Fleming asked the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Clare at planning, construction and post construction phase; the commencement and completion dates for each scheme; the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [45203/15]

View answer

Seán Fleming

Question:

184. Deputy Sean Fleming asked the Minister for Public Expenditure and Reform if he will provide an update with regard to all flood relief schemes in County Tipperary at planning, construction and post construction phase; the commencement and completion dates for each scheme; if he will provide, in tabular form, a breakdown of funding envisaged for all such schemes, as well as the annual funding for such schemes over the 2011-2015 period; and if he will make a statement on the matter. [45204/15]

View answer

Seán Fleming

Question:

185. Deputy Sean Fleming asked the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Waterford at planning, construction and post construction phase; the commencement and completion dates for each scheme; the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [45205/15]

View answer

Seán Fleming

Question:

186. Deputy Sean Fleming asked the Minister for Public Expenditure and Reform the status of all flood relief schemes in County Limerick at planning, construction and post construction phase; the commencement and completion dates for each scheme; the funding envisaged for all such schemes and the annual funding for such schemes in the years 2011 to 2015 in tabular form; and if he will make a statement on the matter. [45206/15]

View answer

Written answers

I propose to take Questions Nos. 181 to 186, inclusive, together.

The following table sets out the details for all major flood relief schemes in the counties indicated at planning, construction and post construction phase, the period of construction, a breakdown of the annual funding for such schemes over the 2011–2015 period.

Scheme

Stage

Period of Construction

Cost €000 2011

Cost €000 2012

Cost €000 2013

Cost €000 2014

Cost €000 2015 *

Co Cork

Mallow North

Construction completed

2008 - 2010

472

285

400

211

24

Mallow South & West

Construction completed

2011 - 2014

4185

3108

987

609

837

Fermoy North

Construction completed

2009 -2011

1021

537

1015

250

79

Fermoy South

Construction completed

2012 - 2015

193

5315

8748

4190

347

Bandon

Tender/Confirmation**

Expected 2016-2018

187

114

562

441

197

Skibbereen

Confirmation**

Expected 2016-2018

-

8

321

-

310

Lower Lee (Cork City)

Design

Expected 2017 - 2021

Blackpool

Design/Public Exhibition

Expected 2017 - 2019

6

0

93

478

296

Glashaboy (Glanmire)

Design

Expected 2017 - 2018

-

-

-

90

-

Douglas/Togher

Design

Expected 2017 - 2018

-

-

-

146

-

Crookstown

Design

Expected 2017 - 2018

-

-

-

-

-

Ballymakeera

Design

Expected 2017 - 2018

5

11

41

3

-

Clonakilty

Detailed Design following Public Exhibition

Expected 2017 - 2018

-

-

3

163

319

Midleton

Appointment of consultants

Expected 2017 - 2018

-

-

-

-

-

County Kerry

N/a

N/a

N/a

N/a

N/a

N/a

N/a

County Clare

Ennis Upper

Construction Completed

2008-2010

2,222

5

-

-

-

Ennis Lower

Construction Substantially complete

2013-2015

169

94

9,659

4,074

765

Ennis South

Design

Expected 2016-2018

-

187

-

-

116

County Tipperary

Templemore

Confirmation**

Expected 2016-2018

-

40

-

125

47

Clonmel West

Complete

2008 – 2010

2014 (separate phase)

3,419

539

331

1,077

178

Clonmel North & East

Complete

2010 - 2012

7,856

3,590

455

121

41

County Waterford

Waterford City Phase 1

Complete

2009-2010

600

63

-

-

-

Waterford City Phases 2,3,4

Substantially complete

2012-2015

-

3,120

3,851

4240

2108

County Limerick

King's Island Limerick City

Design/Environmental Screening and Assessment

Too early to be specific but possible construction in late 2017/early 2018; construction expected to take 18/24 months

-

-

-

691

-

Foynes

About to appoint Contractor

Estimated - Summer 2016

-

-

-

36

-

* Expenditure to end November 2015

** Confirmation = Approval under Arterial Drainage Acts by Minister for Public Expenditure and Reform

The expected construction periods indicated are based on current best estimates having regard to the fact that many schemes are at a very early stage.

In relation to the funding of schemes, the Government has provided a total capital allocation of €430 million for flood risk management over the years 2016-2021 and this will be sufficient to meet the funding requirements of all the above indicated scheme yet to commence construction.

In addition to the above major schemes, the local authorities for the counties concerned may have carried out more localised minor flood relief works either using their own funding or with funding provided through the Office of Public Works Minor Flood Mitigation and Coastal Protection Scheme.