Dáil Éireann Debate, Thursday - 14 April 2016

Thursday, 14 April 2016

Questions (725)

Brendan Smith

Question:

725. Deputy Brendan Smith asked the Minister for Education and Skills the status of an application for new permanent accommodation for a school (details supplied) in County Cavan, including when this project will proceed to the next stage; and if she will make a statement on the matter. [7026/16]

View answer

Written answers

The major building project for the school referred to by the Deputy is at an early stage of architectural planning, Stage 2a - Developed Design Stage.

The Stage 2a Addendum has recently been reviewed by my Department and once a Stage 2a Completion Cert is received the project will be authorised to progress to Stage 2b – Detailed Design Stage, which includes the applications for Planning Permission, Fire Cert and Disability Access Cert and the preparation of Tender Documents and prequalification of contractors.

This project was included in the six year programme announced on 17 November, 2015.