Question:

743. Deputy Brendan Smith asked the Minister for Education and Skills the status of a project (details supplied) in County Cavan; the stage it is at; when it will proceed to the next stage; the timescale for the detailed planning and design work to be undertaken and for commencement of the tendering process; the estimated level of expenditure; if she has made financial provision in her Estimates for this project; and if she will make a statement on the matter. [7220/16]

View answer

Written answers

The Deputy will be aware that a project for the school to which he refers was included in my Department's 6 Year Capital Programme which I announced last November. The project will be progressed with a view to proceeding to tender and construction stages between the years 2019 to 2021, as outlined in the programme.