Schools Building Projects Status

Dáil Éireann Debate, Friday - 16 September 2016

Friday, 16 September 2016

Questions (480)

Seán Fleming

Question:

480. Deputy Sean Fleming asked the Minister for Education and Skills when a school project (details supplied) will be advanced; and if he will make a statement on the matter. [25908/16]

View answer

Written answers

The building project for the school to which the Deputy refers was recently approved to progress to the advanced stage of the architectural planning process, Stage 2(b) - Detailed Design Stage, which includes the applications for planning permission, fire cert and disability access cert and the preparation of Tender Documents.

Once all statutory approvals have been secured, and subject to no further issues arising, the Design team will submit the stage 2(b) report to the Department for review and the Department will revert to the school with regard to the further progression of the project following consideration of that report.