The major school building project to which the Deputy refers is at an advanced stage of architectural planning - Stage 2(b). All statutory approvals have been secured.
However, following the appointment of a replacement Quantity Surveyor, the Design Team in association with the newly appointed Quantity Surveyor prepared a revised Bill of Quantities which has just been received by my Department. My Department will revert to the school with regard to the further progression of the project following consideration of this report.
This project has not yet advanced to a stage where a contract can be signed.