786. Deputy Fergus O'Dowd asked the Minister for Children and Youth Affairs the reports commissioned by her Department since 2006 which while completed or are in final draft form have not been published; the reason they have not been published; the expected publication date; the cost to date of each such report; if tenders were invited; if it is not intended to publish any such report the reason for same; and if she will make a statement on the matter. [37543/16]

View answer

Written answers

My Department was established in June 2011, therefore all information provided to the Deputy is from this date.

Name of Report

Reason for non-publication

Internal Report/To be published

Cost of Report

Tendering Process Undertaken

Public Knowledge and attitudes relating to children’s rights, welfare, protection and services

Internal use only

Internal Report

€103,011.98

Yes

Issues for consideration in developing an on-line resource to support implementation of QCBI and preliminary Roadmaps (scoping project on data sources relating to children)

Internal use only

Internal Report

€20,932.79

Yes

Comhairle na nÓg and Garda Síochána survey on the Attitudes of Gardaí to Young People. Questionnaire for Gardaí and Young People

Internal use only

Internal Report

€7,650.00

Yes

Report on the process, methodology and work of the Comhairle na nÓg National Executive 2014-2015

Internal use only

Internal Report

€7,915.05

Yes

Audit of education and training on children’s rights and children’s and young people’s participation in decision-making in all third level and further education programmes and continuing professional development programmes in Ireland

Internal use only

Internal Report

€19,978.00

Yes

A review of public policy on play and recreation in Ireland

Internal use only

Internal Report

€13,200.00

Yes

Report of the workshop discussions at the Comhairle na nÓg Showcase 2016

December 2016

€9,203.00

Yes

Report of consultations and meetings of Phase 1 of the Children’s Poverty Truth Commission

July 2017

Per diem rate – number of days to be determined

Yes

Report of Evaluation of Phase 1 of the Children’s Poverty Truth Commission

July 2017

Per diem rate – number of days to be determined

Yes

Strategic Human Resources

Internal use only

Internal Report

€20,602.50

Yes

Needs Assessment for the Redevelopment of www.childrensdatabase.ie

Internal use only

Internal Report

€18,400.00

No

"Becoming an Active Player" - Report on meeting of Better Outcomes, Brighter Futures Advisory Council

Internal use only

Internal Report

€1,600.00

No

Care Issues Review

Internal use only

Internal Report

€3,556.56

No

Report on Structural Damage

Internal use only

Internal Report

€7,668.74

Yes

Staff Roster Review

Internal use only

Internal Report

€6,715.80

Yes

Care issues Review

Internal use only

Internal Report

€13,636.21

No

Care Issues Review

Internal use only

Internal Report

€13,500.00

Yes

Policy Analysis and Development on Remission of Sentence

Internal use only

Internal Report

€29,151.00

No

Land Valuation Report

Internal use only

Internal Report

€2,152.50

Yes

Valuation Report

Internal use only

Internal Report

€1,230.00

No

Internal Audit Report: Early Childhood Care and Education Scheme & Audit Report on ICT Shared Services Arrangements

Internal use only

Internal Report

€23,803.00

Yes

Internal Audit Report: Community Childcare Subvention/Childcare Education & Training Supports Programmes

Internal use only

Internal Report

€8,200.00

Yes

Internal Audit Report: National Children's Detention Facility

Internal use only

Internal Report

€12,623.00

Yes

Internal Audit Report: Programme Integration

Internal use only

Internal Report

€16,858.00

Yes

Internal Audit Report: Programme Integration Platform

Internal use only

Internal Report

€15,675.00

Yes

CFA Governance Audit

Internal use only

Internal Report

€23,468.50

Yes

Policies & Procedures Review

Internal use only

Internal Report

€4,125.00

Yes

Report of Ireland's Implementation of EU Youth Strategy

Internal & EU use only

Internal Report

€6,300.00

Yes

National Consultation with Children (Aged 3-5) on the National Early Years Strategy

Report not yet finalised

Report not finalised

€23,865.00

No

Evaluation of the strategic options to deliver an ICT system to support the Single Affordable Childcare Scheme

Internal use only

Internal Report

€27,950.00 - Phase 1

Yes

Top
Share