Dáil Éireann Debate, Friday - 16 December 2016

Friday, 16 December 2016

Questions (399)

Billy Kelleher

Question:

399. Deputy Billy Kelleher asked the Minister for Health the primary care centre projects announced on 17 July 2012, in tabular form; the current status of same; and if he will make a statement on the matter. [40955/16]

View answer

Written answers

The Programme for a Partnership Government sets out a clear vision for our health services which is community based and responsive and accessible to patients. Supporting infrastructure, procured through a combination of public and private investment, will facilitate the delivery of multi-disciplinary primary health care. However, while the Government's objective is to deliver a high quality, integrated and cost effective health care service the mechanism and timescale for delivery of primary care centres is dependent on a number of factors. Some of these factors are outside the control of the Health Service Executive. Regardless of the delivery mechanism, all potential primary care infrastructure is subject to suitable locations being offered / provided / available, to successful planning processes and GP commitment to sharing accommodation and delivering health care services with HSE staff. In addition the operational lease mechanism is subject to market pressures such as the developers' access to adequate financing.

Delivery of primary care infrastructure is a dynamic process, constantly evolving to take account of changing circumstances including the feasibility of implementation. The current status of the projects is set out in the table below. However, it should be noted that 54 primary care centres have been opened since 2011. In addition, to the primary care centres shown in the table below as scheduled shown in 2017, a further 16 primary care centres are planned to open in 2017 or early 2018.

Primary Care Centres: July 2012 announcement - 35 locations

Count

HSE Region

County

Location / PCT Name

Delivery Mechanism

Project Status - Q3 2016 PQ40955/16: answer date 13/12/2016

1

DML

Dublin

Rowlagh / North Clondalkin

Direct build

Stage 2a design team report completed. HSE finalising purchase agreement of site at Collinstown Park School. Purchase agreement is subject to planning permission being granted for the development.

2

DML

Dublin

Crumlin / Drimnagh

Direct build

Planning permission in place

3

DML

Dublin

Knocklyon / Rathfarnham

Direct build

Planning permission in place

4

DML

Wicklow

Rathdrum

Operational Lease

Planning approved. HSE has finalised layouts. Construction due to commence to commence Q1 2017 and projected to open Q2 2018

5

DML

Kildare

Kilcock

PPP

In construction. Projected opening 2018

6

DNE

Dublin

Coolock / Darndale

PPP

In construction. Projected opening 2018

7

DNE

Dublin

Summerhill, north inner city Dublin

PPP

In construction. Projected opening 2018

8

DNE

Dublin

Balbriggan

Operational Lease

Construction due to be completed Q4 2016, projected to open Q1/Q2 2017

9

DNE

Dublin

Swords

Operational Lease

Preferred site sold. New advertisement required.

10

DNE

Louth

Drogheda north

Operational Lease

Developer re-engaged. Existing building requires fitout. If legal discussions complete successfully, projected completion Q4 2017 and operational Q1 2018.

11

DNE

Meath

Laytown and Bettystown

Operational Lease

Project is progressing as operational lease. Schedule of accommodation under review

12

DNE

Meath

Kells

Operational Lease

Operational Q12016

13

DNE

Monaghan

Carrickmacross

Operational Lease

Viable expression of interest has recently been received. Currently waiting for formal submissions.

14

South

Carlow

Tullow / Rathvilly / Hacketstown

Direct build

Adjoining landowner has re-engaged with HSE. Options being reviewed.

15

South

Kilkenny

Kilkenny city (East)

Operational Lease

Priced offer approved. Letter of Intent issued.

16

South

Wexford

Wexford town

PPP

In Construction. Projected opening 2018

17

South

Waterford

Dungarvan

PPP

In Construction. Projected opening 2018

18

South

Waterford

Waterford city (east)

PPP

In Construction. Projected opening 2018

19

South

Cork

Cork city - Ballyphehane / Togher /

Greenmount / The Lough

Operational Lease

Stage 3 submissions under review

20

South

Kerry

Tralee

Operational Lease

Stage 3 submissions under review

21

South

Tipperary

Carrick-on-Suir

PPP

In Construction. Projected opening 2018

22

South

Tipperary

Clonmel

Operational Lease

Awaiting stage 3 submissions

23

West

Tipperary

Thurles

Operational Lease

Letter of Intent issued 10/12/2015. Project progressing towards Agreement for Lease.

24

West

Limerick

Limerick city (Ballinacurra / Weston)

PPP

In Construction. Projected opening late 2017

25

West

Clare

Ennis

Operational Lease

Re-advertisement to be considered

26

West

Galway

Tuam

PPP

In Construction. Projected opening late 2017

27

West

Galway

Gort

Operational Lease

Letter of Intent withdrawn 24/05/2016. Possible re-advertisement.

28

West

Roscommon

Boyle

PPP

In Construction. Projected opening late 2017

29

West

Roscommon

Ballaghadereen

Operational Lease

Letter of Intent issued 27/10/2015. Project progressing to Agreement for Lease.

30

West

Mayo

Westport

PPP

In Construction. Projected opening 2018

31

West

Mayo

Claremorris

PPP

In Construction. Projected opening late 2017

32

West

Sligo

Ballymote

PPP

In Construction. Projected opening late 2017

33

West

Donegal

Dungloe

Operational Lease

Seeking re-advertisement for Operational Lease option

34

West

Donegal

Donegal town

Operational Lease

Re-advertisement required

Coolock and Darndale were announced as two separate locations