Skip to main content
Normal View

Social and Affordable Housing Applications Data

Dáil Éireann Debate, Thursday - 23 February 2017

Thursday, 23 February 2017

Questions (217)

John Curran

Question:

217. Deputy John Curran asked the Minister for Housing, Planning, Community and Local Government the original date of application for each application for social housing made to his Department; the number of units in each application; the status of each application; when construction commenced or is due to commence; when each development is expected to be completed, or has been completed, by local authority in tabular form; and if he will make a statement on the matter. [9137/17]

View answer

Written answers

On Monday last, I published a Social Housing Construction Projects Status Report, which lists all approved projects including those delivered in 2016 and those at various stages of advancement through planning, design and construction. This report can be seen at the following link:

www.housing.gov.ie/sites/default/files/publications/files/rebuilding_ireland_-_social_housing_construction_status_report_-_q4_2016.pdf.

The report contains a range of information in relation to each separate social housing construction project, including the local authority area, project name, AHB name where applicable, the number of units and the status of each application in terms of its current level of advancement.

Top
Share