Flood Prevention Measures

Dáil Éireann Debate, Wednesday - 1 March 2017

Wednesday, 1 March 2017

Questions (229)

Brendan Ryan

Question:

229. Deputy Brendan Ryan asked the Minister for Public Expenditure and Reform when the work will be completed on the flood prevention work on City Quay, Dublin 2. [10556/17]

View answer

Written answers

The South Campshires Flood Protection Project started construction in November, 2014. These works are ongoing on the south quays of the River Liffey and are due to be substantially completed at the end of Q3 2017. The works extend from Butt Bridge, at the upstream extent, to a point 130 metres downstream of Samuel Beckett Bridge at the downstream extent - a distance of approximately 1,050 metres.

The scheme, when completed, will protect a large flood cell with significant business, retail and densely populated residential areas.