Skip to main content
Normal View

Social and Affordable Housing Provision

Dáil Éireann Debate, Thursday - 9 March 2017

Thursday, 9 March 2017

Questions (149)

Barry Cowen

Question:

149. Deputy Barry Cowen asked the Minister for Housing, Planning, Community and Local Government if 24 or 53 rapid build units are planned for construction in Cherry Orchard, in view of the fact that according to Dublin City Council it is 24 units but according to his Department it is 53 units; the reason for this disparity; and if he will make a statement on the matter. [12692/17]

View answer

Written answers

There are two separate Rapid Build schemes in Cherry Orchard. It is expected that the first scheme of 24 units will be completed and delivered by the end of Quarter 2, 2017. The second scheme, comprising 53 units, is currently at tender stage and is expected to be completed later this year.