Primary Care Centres Provision

Dáil Éireann Debate, Thursday - 13 July 2017

Thursday, 13 July 2017

Questions (676)

Billy Kelleher

Question:

676. Deputy Billy Kelleher asked the Minister for Health the primary care centre projects announced on 17 July 2012; the status of same; and if he will make a statement on the matter. [33952/17]

View answer

Written answers

Delivery of primary care infrastructure is a dynamic process, which evolves to take account of changing circumstances including the feasibility of implementation.

The following table gives details of the 35 locations announced on 17 July 2012, and their current status including estimated opening dates. One of these primary care centres is already operational and a further six are projected to open in 2017, and ten in 2018.

In addition, it should be noted that 57 primary care centres have been opened since 2011, and a further 12 primary care centres are projected to open in 2017 or early 2018, in addition to those shown in the following table.

Count

HSE Region

County

Location/PCT Name

Delivery Method

Project Status - Q1-Q2 2017

1

DML

Dublin 

Rowlagh/North Clondalkin

Direct build

Stage 2a design team report completed.  HSE finalising purchase agreement of site at Collinstown Park School.  Purchase agreement is subject to planning permission being granted for the development.  

2

DML

Dublin 

Curlew Road/Crumlin/Drimnagh

Direct build

Planning permission in place

3

DML

Dublin 

Knocklyon/Rathfarnham

Direct build

Planning permission in place

4

DML

Wicklow

Rathdrum 

Operational Lease

Planning approved.  HSE has finalised layouts.  Construction due to commence to commence Q2 2017 and projected to open Q3 2018

5

DML

Kildare

Kilcock

PPP

In construction. Projected opening 2018

6

DNE

Dublin 

Coolock/Darndale

PPP

In construction. Projected opening 2018

7

DNE

Dublin 

Summerhill, north inner city Dublin

PPP

In construction. Projected opening 2018

8

DNE

Dublin 

Balbriggan

Operational Lease

Construction completed Q2 2017, projected operational Q3 2017

9

DNE

Dublin 

Swords

Operational Lease

Expressions of interest received. Currently being reviewed

10

DNE

Louth

Drogheda north

Operational Lease

Developer re-engaged.  Existing building requires fitout. If legal discussions complete successfully, projected construction start Q2/Q3 2017, projected completion Q1 2018 and operational Q2 2018.

11

DNE

Meath

Laytown and Bettystown

Operational Lease

Project is progressing as operational lease.  Schedule of accommodation under review

12

DNE

Meath

Kells

Operational Lease

Operational since Q1 2016

13

DNE

Monaghan

Carrickmacross

Operational Lease

Viable expression of interest has recently been received.  Currently waiting for formal submissions.  

14

South

Carlow

Tullow/Rathvilly/Hacketstown

Direct build

Adjoining landowner has re-engaged with HSE.  Options being reviewed.

15

South

Kilkenny

Kilkenny city (East)

Operational Lease

Priced offer approved.  Letter of Intent issued.

16

South

Wexford

Wexford town

PPP

In Construction. Projected opening 2018

17

South

Waterford

Dungarvan

PPP

In Construction. Projected opening 2018

18

South

Waterford

Waterford city (east)

PPP

In Construction. Projected opening 2018

19

South

Cork

Cork city - Ballyphehane/Togher/Greenmount/The Lough

Operational Lease

Letter of Intent issued. Layouts being developed.

20

South

Kerry

Tralee

Operational Lease

Letter of Intent issued. Layouts being developed.

21

South

Tipperary

Carrick-on-Suir

PPP

In Construction. Projected opening 2018

22

South

Tipperary

Clonmel

Operational Lease

Reviewing accommodation requirements before progressing to stage 3

23

West

Tipperary

Thurles

Operational Lease

Letter of Intent issued 10/12/2015.  Project progressing towards Agreement for Lease. 

24

West

Limerick

Limerick city (Ballinacurra/ Weston)

PPP

In Construction. Projected opening late 2017

25

West

Clare

Ennis

Operational Lease

Expressions of interest received. Currently being reviewed

26

West

Galway 

Tuam

PPP

In Construction. Projected opening late 2017

27

West

Galway 

Gort

Operational Lease

Letter of Intent withdrawn  24/05/2016.  Possible re-advertisement.

28

West

Roscommon

Boyle

PPP

In Construction. Projected opening late 2017

29

West

Roscommon

Ballaghadereen

Operational Lease

Letter of Intent issued 27/10/2015.  Project progressing to Agreement for Lease.

30

West

Mayo

Westport

PPP

In Construction. Projected opening 2018

31

West

Mayo

Claremorris

PPP

In Construction. Projected opening late 2017

32

West

Sligo

Ballymote

PPP

In Construction. Projected opening late 2017

33

West

Donegal

Dungloe - An Clochán Liath

Operational Lease

Re-advertised for Operational Lease option. Expressions of interest received.

34

West

Donegal

Donegal town

Operational Lease

Expressions of interest received. Currently being reviewed

  Coolock and Darndale were announced as two separate locations 

 

The mechanism and timescale for delivery of primary care centres is dependent on a number of factors. Some of these factors are outside the control of the Health Service Executive. Regardless of the delivery mechanism, all potential primary care infrastructure is subject to suitable locations being offered / provided / available, to successful planning processes and GP commitment to sharing accommodation and delivering health care services with HSE staff. In addition the operational lease mechanism is subject to market pressures such as the developers' access to adequate financing.