Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Monday - 11 September 2017

Monday, 11 September 2017

Questions (342, 391, 395)

Jack Chambers

Question:

342. Deputy Jack Chambers asked the Minister for Education and Skills the position regarding plans to build a new school for a school (details supplied) which was promised in 2007; and if he will make a statement on the matter. [37532/17]

View answer

Joan Burton

Question:

391. Deputy Joan Burton asked the Minister for Education and Skills the progress of the rebuild of a school (details supplied); the stage it is at; the timeframe of construction; when groundworks will commence; and if he will make a statement on the matter. [38073/17]

View answer

Joan Burton

Question:

395. Deputy Joan Burton asked the Minister for Education and Skills the stage the redevelopment and new buildings for a school (details supplied) is at; and if he will make a statement on the matter. [38077/17]

View answer

Written answers

I propose to answer Questions Nos. 342, 391 and 395 together.

The major school building project to which the Deputy refers is at an advanced stage of architectural planning - Stage 2(b). All statutory approvals have been secured.

However, following the necessary appointment of a replacement Mechanical & Electrical Engineer the Design Team in association with the newly appointed Engineer are working on a revised MandE report which will be submitted to the Department when it is completed.

Upon receipt and review of the report my Department will revert to the Board of Management with regard to the further progression of the project at that time.

Top
Share