200. Deputy Pat The Cope Gallagher asked the Minister for Education and Skills when he expects a school (details supplied) to go to tender stage for the new school building; the timeframe for project delivery; and if he will make a statement on the matter. [41910/17]

View answer

Written answers

The major building project for the school to which the Deputy refers is at an advanced stage of architectural planning - Stage 2(b) - Detailed Design.  The design team are currently working on completing Stage 2(b) of the architectural planning process. When complete, the stage 2(b) report will be submitted to my Department. When this submission has been received and reviewed, my Department will then be in further contact with the school authorities as regards the progression of the project to tender stage.