Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Thursday - 23 November 2017

Thursday, 23 November 2017

Questions (104)

Aindrias Moynihan

Question:

104. Deputy Aindrias Moynihan asked the Minister for Education and Skills the expected commencement date for the construction of a school (details supplied) in County Cork; and if he will make a statement on the matter. [49743/17]

View answer

Written answers

The building project for the school referred to by the Deputy has been tendered and a preferred bidder was initially selected. However, before the project proceeded to site the preferred bidder withdrew from the tender competition.

The Design Team is currently examining the 2nd lowest tender and subject to no issues arising it is envisaged that the project will commence on site early in 2018.