Schools Building Projects

Dáil Éireann Debate, Tuesday - 16 January 2018

Tuesday, 16 January 2018

Questions (424)

Joan Burton

Question:

424. Deputy Joan Burton asked the Minister for Education and Skills if tenders have been invited for a project (details supplied); if so, the closing date for receipt of tenders; when construction of the new school is likely to commence; and if he will make a statement on the matter. [1522/18]

View answer

Written answers

The building project referred to by the Deputy is for a new 24 classroom school including a Special Needs Unit, with a floor area of approx. 4,748m2.

The project is currently at Stage 2B of Architectural Planning - Detailed Design Stage, which includes applications for all statutory consents, including Planning Permission, Disability Access Certificate and Fire Safety Certificate and also the preparation of tender documentation. Planning Permission for this project was received in August of this year.

The Stage 2B report has just recently been received and reviewed by my Department.  A number of issues were identified as needing clarification by the Design Team prior to approval of the Stage 2B submission.

Once a revised Stage 2B submission which addresses these issues has been received and reviewed, my Department will then revert to the school with regard to a timeframe for progression to tender.