Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 6 February 2018

Tuesday, 6 February 2018

Questions (188)

Thomas Byrne

Question:

188. Deputy Thomas Byrne asked the Minister for Education and Skills when commencement of a new building for a school (details supplied) will take place. [5519/18]

View answer

Written answers

The major building project for the school referred to by the deputy has reached an advanced stage of architectural planning, Stage 2(b), which includes the pre-qualification of contractors and the preparation of tender documents.

In May 2017, my Department gave approval to the school authorities to have their Design Team commence the process of Pre-Qualification of Contractors. The Design Team has informed my Department that this process is now complete.

The Design Team has also informed that it is currently working on completing a revised Stage 2 (b) submission which it expects to submit for review by my Department shortly.  Upon review of the revised submission, my Department will revert to the school with a timeframe for progression of the project to tender stage.

Top
Share