216. Deputy Joan Burton asked the Minister for Education and Skills if tenders have been invited for a project (details supplied); if the closing date for receipt of tenders is available; when construction of the new school is likely to commence; and if he will make a statement on the matter. [5912/18]

View answer

Written answers

The major building project for St. Joseph's National School in Kilcock is at an advanced stage of architectural planning Stage 2b (Detailed Design), which includes the application for statutory approvals and the preparation of tender documents. All statutory approvals have been secured.

The Stage 2b submission has been reviewed by my Department and comments have issued to the school and its Design Team. My Department requested confirmations from the Design Team that it carries out one final review of all of its tender documentation to ensure compliance with DoES requirements. The Design Team has been requested to submit written confirmation from each Design Team member including the PSDP that they have completed this review and are satisfied that the Tender Documents are complete, correct and in compliance with DoES and Building Control (Amendment) Regulations (BC(A)R) tender documentation requirements.

These confirmations have recently been received and my Department will shortly revert to the school with regard to the further progression of the project.