Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 17 April 2018

Tuesday, 17 April 2018

Questions (357)

Fergus O'Dowd

Question:

357. Deputy Fergus O'Dowd asked the Minister for Education and Skills the status of the major building project at a school (details supplied); and if he will make a statement on the matter. [15381/18]

View answer

Written answers

The major building project referred to by the Deputy is at an advanced stage of architectural planning, Stage 2(b) - Detailed Design, which includes the applications for Planning Permission, Fire Cert and Disability Access Cert and the preparation of tender documents. All statutory approvals have been obtained.

In May 2017, the Department gave approval to the school authorities to have their Design Team commence the process of Pre-Qualification of Contractors and the Department has been informed by the Design Team that this process is complete.

The Design Team has recently submitted a revised Stage 2(b) submission to my Department. Upon review of this submission and providing no issues arise, my Department will revert to the school with a timeframe for progression of the project to tender stage.

A tender stage normally takes between 7 and 8 months to complete. A letter recently issued from my Department to the school and its Design Team outlining the projected timeframe for progression of this project to tender and construction stage and the steps involved.