Schools Building Projects Status

Dáil Éireann Debate, Friday - 7 September 2018

Friday, 7 September 2018

Questions (243)

Joan Burton

Question:

243. Deputy Joan Burton asked the Minister for Education and Skills if he has received the pre-qualification report from the design team in relation to a school (details supplied); when a preferred tenderer will be chosen; and if he will make a statement on the matter. [35487/18]

View answer

Written answers

As the Deputy is aware, the project to which she refers has been devolved for delivery to Kildare and Wicklow Education & Training Board (ETB).

The pre-qualification report from the Design Team is due to be completed and submitted to the ETB in mid October 2018.  It is not possible to say at this stage when the preferred tenderer will be chosen.