387. Deputy Thomas Byrne asked the Minister for Education and Skills the position regarding an extension to a school (details supplied) and the tender and construction project for same. [36867/18]

View answer

Written answers

The project to which the Deputy refers has been approved and devolved for delivery to the local Education and Training Board (ETB) under my Department's Additional Accommodation Scheme. The design team that the ETB has appointed for this project is currently preparing tender documentation. The completion of this documentation will allow the process of tendering for the completion of the contract to begin. This is expected to take place before the end of October. Once this tendering process is complete, the works can then proceed to site.