The following is a summary of the number of cases awaiting decision by An Bord Pleanála for six-monthly periods in excess of 6 months as at end September 2018:
On Hands Period
|
Number of Cases - All Case Types
|
>6 months <12 months
|
247
|
>12 months <18 months
|
26
|
>18 months <24 months
|
23
|
>24 months
|
35*
|
Total
|
331
|
* This figure includes 19 pre-application consultation cases in relation to proposed strategic infrastructure development where the prospective applicant has requested that An Bord Pleanála maintains the case as open and which accordingly does not proceed to a determination as to whether the proposed development qualifies as strategic infrastructure development.
It should also be noted that many of the cases on hand for extended periods of time arise from the issuing of further information requests by the Board in order to be able to more comprehensively assess the cases in question. In this regard, there can be delays in the submission of the requested information to the Board by the parties concerned which, on receipt, must then be further circulated to other parties in the case.